1 August 2013

The installation works of first GPU -32 «Ladoga» have been started on the CS «Syninskaya»

At July of 2013 is begun installation of the first GPU «Ladoga-32» on the CS-7 «Syninskaya» the first brunch of gas main «Bovanenkovo - Ukhta». Experts of «REP Holding» carry out technical supervision of the GPU directly on site.

The unit was made by the order of «YMALGAZINVEST under a contract with «Gazprom Komplektatsiya» for the supply of 19 pcs. of GPU -32 «Ladoga» - 16 pcs. of GPU on four compressor stations of the first line of the main gas pipeline «Bovanenkovo - Ukhta», Two of the units at CS «Vavozhskaya » and one on CS «GRYZOVETS». Manufacture one GPU takes about 15 months, but the production facilities of «REP Holding» allow manufacturing more units at a time, which provides possibility to complete orders more quickly.

For CS «Syninskaya» 4 units of GPU were produced, which, after successful AT (acceptance tests) were shipped to the object in the middle of 2012. Installation of main and auxiliary equipment, as well as commissioning units will be completed within 9 months, after which the tests will be put into commercial operation. Wheel GPU-32 «Ladoga» is gas-turbine MS5002E made on the basis of the license agreement between «REP Holding» and GE Oil & Gas (NP). Units for CS «Syninskaya» were manufactured at the production sites of «REP Holding » in various phases of localization - three turbines were manufactured for the second phase and one - third of the final phase of localization of production of MS5002E gas turbine.

Currently all 16 units shipped at the compressor stations of the first line of the main gas pipeline «Bovanenkovo - Ukhta» - on CS «Chickshinskay» 4 GPU-32 «Ladoga» was put into operation, the ends installation and being commissioning of 4 units at CS «Maloperanskaya» and 4 units at the CS «Intinskaya». For the second line of the MG «Bovanenkovo - Ukhta» «REP Holding» will produce 12 gas-pumping units.

Back to the news