30 July 2013

«REP Holding» successfully tested the first GTU MS5002E for CS «Russkaya»

At 25-th of July at the facilities of production site of «REP Holding» - «Nevskiy Zavod» - passed AT (acceptance tests) of the first of a GTU MS5002E for compressor station «Russkaya» of main gas pipeline «South stream». This MS5002E gas turbine manufactured by the third and final phase of the license agreement between CJSC «REPH» and GE Oil&Gas (NP).

In the April of 2012, «REP Holding» has signed the Contract with «Gazprom Komplektatsiya» on manufacture and delivery of 14 pcs. of GPU-32 «Ladoga», driver to which is GTU MS5002E , for the world's largest compressor station «Russkaya». Under the terms of the contract by the end of 2013 year will be completed production of the first seven units, the final execution of the order planned by the end of 2015 year.

Tests were carried out in the presence of representatives of «Gazprom VNIIGAZ», «Gazprom Transgaz Krasnodar», «Gazprom Invest», «Orgenergogaz». Program and methodology of acceptance tests developed by CJSC «IEMET» (the subsidiary company of «REP Holding»), agreed with Gazprom and «Gazprom VNIIGAZ». The tests were performed under load for more than 5 hours. In tests of GTU МS5002Е compliant, the thermal and mechanical characteristics of the technical requirements - efficiency with the power to 31,2 MW was 36,3%.

Is currently preparing GTU for shipment to CS «Russkaya», which is scheduled for August 2013. In the production is six gas turbine units in a state of readiness more than 50%.

Back to the news