23 January 2012

GTU MS5002E assembled at «REP Holding» has been accepted for operation

On January, 17 and 18, 2012, at REP Holding, on the Nevsky Zavod production site successfully passed the acceptance – delivery tests of the MS 5002E gas turbine. This turbine is supplied as a drive for the GPU-32 «Ladoga» to the main gas pipeline «Bovanenkovo-Ukhta».

The tests performed have confirmed the operability and the performance of the MS 5002E GTU in the scope of the program and procedure of the acceptance – delivery tests.

This gas turbine unit is the first one assembled at the REP Holding facilities and manufactured in accordance with the MS 5002E localization phases within the frame of the implementation of the License Agreement with General Electriс Oil & Gas Nuovo Pignone.

The tests were witnessed by the commission representing «Gazprom Transgaz Ukhta», «Gazprom VNIIGAZ», «Yamalgazinvest», as well as «REP Holding» and its subsidiaries –«Nevskiy Zavod» and «Institute of Power Machine-Building & Electronics» - under the chairmanship of Igor Starinkov, Vice-President of «REP Holding».

The acceptance – delivery tests were performed on the operating unit according to the program and procedure developed by the «IPM&E» («REP Holding» subsidiary) and agreed upon with «Gazprom», «Gazprom VNIIGAZ» и General Electriс Oil&Gas Nuovo Pignone.

Based on the results and on the data obtained the Acceptance Test Report was signed, whereby the commission stated that this MS 5002E gas turbine unit can be shipped to the customer and used by «Gazprom» as a gas turbine drive of the GPU-32 «Ladoga» at the main gas pipeline «Bovanenkovo-Ukhta» compressor stations.

Back to the news